12 13
2.4. Single UPS installaon
Installation and wiring must be carried out in accordance with the local
electric laws and regulations by trained professionals.
Step 1. Make sure that the mains wire and breakers of the building are
rated for the capacity of the UPS to prevent electric shock or risk of fire.
NOTE!
Step 2. Switch off the mains switch in the building before installation.
Step 3. Turn off all the connected devices before connecting to the UPS.
Step 4. Prepare wires based on the following table:
Model Wiring spec (minimum A cable should support)
Input (Ph) Output (Ph) Neutral Baery Cabinet Ground
Garun 30KL 50A 50A 85A 105A 50A
Garun 40KL 65A 65A 110A 140A 65A
• The cables for Garun 30KL should be able to withstand over 50A current
for Input and Output phase, 85A for Neutral, 105A for battery cabinet and
50A for Ground. Please use corresponding thickness for each wire.
• The cables for Garun 40KL should be able to withstand over 65A current
for Input and Output phase, 110A for Neutral, 140A for battery cabinet and
65A for Ground. Please use corresponding thickness and composition for
each wire.
Step 5. Remove the terminal block cover at the rear panel of UPS. Then
connect the wires according to the following terminal block diagrams:
Diagram 3: Terminal block wiring diagram for Garun 30KL, 40KL
NOTE!
Please install the output breaker between the output terminal and the load,
and the breaker should be qualified with leakage current protective function
if necessary.
Baery wire connect schemac in addional baery cabinet
Battery wire connect
schematic
• Make sure that the wires between UPS and battery cabinet are connected
tightly.
Step 6. Put the terminal block cover back at the rear panel of the UPS.
IMPORTANT!
• Make sure a DC breaker or other protective device between UPS and the
external battery pack is installed. If not, please install it carefully. Switch off
the battery breaker before installation.
• Set the battery pack breaker in “OFF” position and then install the battery pack.
• Pay high attention to the rated battery voltage marked on the rear panel.
If you want to change the numbers of the battery pack, please make sure
you modify the setting simultaneously. The connection with wrong battery
voltage may cause permanent damage of the UPS. Make sure the voltage of
the battery pack is correct.
• Pay high attention to the polarity marking on external battery terminal
block. And make sure the correct battery polarity is connected. Wrong
connection may cause permanent damage of the UPS.
• Make sure the protective earth ground wiring is correct. The wire current
spec, color, position, connection and conductance reliability should be
checked carefully.
• Make sure the utility input & output wire is correct. The wire current spec,
color, position, connection and conductance reliability should be checked
carefully. Make sure the L/N side is correct, not reverse or short-circuited.