Easee Charging Robot Instrucciones de montaje

Easee Home
Easee Charge
EN Installer guide

2
Introduction
Read the Important product information guide in the
product packaging or at easee.com/manuals before
installing the product.
Installation and operation of the product require a
mobile device with internet connection.
WARNINGS AND CAUTIONS
A Warning indicates a condition, hazard or unsafe
practice that can result in serious personal injury or
death.
A Caution indicates a condition, hazard or unsafe
practice that can result in minor personal injury or
damage to the product.
WARNING
This product shall only be installed, repaired or serviced
by an authorised electrician. All applicable local, regional
and national regulations for electrical installations must
be respected.
NOTE
PIN code: The PIN code is required for installation and
located on the front of the Chargeberry.
It is recommended to keep the PIN code for safe keep-
ings, e.g inside the fuse cabinet.

3
Product overview
Installation kit Tool
x 5Sealing plug
x 2
Blind plug
x 3
x 4Strain relief
x 2
x 1
Front cover
Protects the electronics from
external influences.
Chargeberry
Contains the electronics
for charging the vehicle.
Backplate
For attaching and connecting to
the charging infrastructure.

4
Technical specifications
General
Dimensions 256 x 193 x 106 mm (H x W x D)
Wall mounting c/c 160 x 125 mm (H x W)
Operating temperature -30 °C to +50 °C
Weight 1.5 kg
Sensors and indicators
Light strip with LEDs showing the status of the charger
Touch button
Temperature sensors in all main contacts
Charging
Charging power 1.4–22 kW
6 A 1 phase – 32 A 3 phase
(automatically adjusted in relation to available capacity)
Up to 7.36 kW at 32 A 1 phase
Up to 22 kW at 32 A 3 phase
Connection point Type 2 socket (IEC 62196-2)
Number of phases 1 or 3 (fully dynamic)
Voltage 3x 230/400V AC (±10%)
Mains frequency 50/60 Hz
Easee Home Load balancing of up to 3 units per circuit
Easee Charge Load balancing of up to 101 units per circuit
Built-in energy meter (±2 %)

5
Connectivity
Built-in eSIM (LTE Cat M1/ 2G /GPRS)
WiFi 2.4 GHz b/g/n connection
Easee Link RFTM
Control charging via Easee App
RFID/NFC reader
OCPP 1.6 via our API
Protection
Integrated overload protection according to EN IEC 61851-1:2019
Built-in RCD for ground fault protection (30 mA AC/ 6 mA DC) according to EN 61008-1 and IEC 62955
Degree of protection IP54 (the backplate is IP22 without cover)
Impact resistance IK10
Insulation class II
Overvoltage category III
Installation
Installation network TN, IT or TT (detected automatically)
Installation circuit breaker Max 40 A (Easee Home) and 80 A (Easee Charge)
Wire cross-section up to 16 mm2(single cable)/
up to 10 mm2(parallel connection)
Cable diameter 8–22 mm
Terminal torque 5 Nm
Cable strip length 12 mm

6
Planning the installation
Prior to the installation, it is recommended that you
consider future charging needs, so that you can easily
expand accordingly in the future.
If several Charging Robots are connected to the same
circuit, the total current is dynamically distributed
between them. The connected Charging Robots
communicate wirelessly between each other, ensuring
the circuit is not overloaded. The maximum charging
current is set during configuration.
For an optimal result
— We always recommend a 3 phase installation if
possible, to make it future-proof.
— If possible, use the largest approved cable cross-
section (see Technical specifications).
— Consider the installation of Easee Ready backplates
if the acquisition of further Charging Robots is
planned for the future.
— To avoid overloading the building's main fuse, the
Easee Equalizer can be used for dynamic load
balancing. The maximum current value can also be
set as required during configuration.
Special notes
— Several backplates can be connected in parallel, as
each Charging Robot has its own protective device.
— If the charging infrastructure includes more than one
Charging Robot, the backplate that is configured
first becomes the master of its circuit.
— If more than 2 units are installed, the master unit
should be located in the middle of the installation (if
possible) for an optimal Easee Link communication.
— Site Key: During installation, a Site Key must
be used to assign the Charging Robots to the
correct location in the Easee Cloud. A Site Key will
automatically be generated when creating a new
charging site using the Easee Installer App or it can
be obtained by creating a new charging site at
easee.cloud.
Your house, power grid and EV
The Charging Robot automatically adapts to the power
grid, the electric car and the capacity of the electrical
installation. In the table you can see what charging
effect you can expect from your installation and
situation. The table is only meant as a guide.
CAUTION
The type of installation as well as cable cross-sections
must be determined by a qualified electrician in
accordance with valid local, regional and national
regulations for electrical systems.
Load Charging power
Ampere (A) 1 phase (kW) 3 phase (kW)1
6 1.4 4.1
8 1.8 5.5
10 2.3 6.9
13 3.0 9
16 3.7 11
20 4.6 13.8
25 5.8 17.3
32 7.4 22
1Example for 400 V TN, deviating values for other grid
types.
Padlock
It's possible to lock the electronics with a padlock. This
will create an extra layer of security (padlock is not
included).
Max total lock height 56 mm
Shackle height (outer dimensions) 19 - 20 mm
Shackle thickness 3.2 - 4 mm

7
Residual Current Device (RCD)
— A Residual Current Device is integrated in the
Charging Robot.
— The RCD will break the current in case a residual
current exceeding 6mA DC or 30mA AC is detected.
— Disconnection time is according to EN 61008-1 and
IEC 62955.
— The RCD is automatically tested between each
charging session or at least every 24h.
— For manual initialization of the RCD-test, please
refer to the Installer App.
— The integrated RCD has no influence on the function
of external protective devices.
— An external RCD is required when at least one of the
below conditions are identified:
• The installation, including cable, junction boxes
etc., includes components with only basic
insulation (Class I).
• Any other electrical equipment apart from Easee
Home/Charge, including lamps and socket outlets,
is connected to the circuit.
• Any other conditions identified by the authorized
installer requiring an external RCD.
— The internal RCD is considered to provide the
required RCD protection for both AC and DC leakage
faults when all the below conditions are fulfilled:
• The installation, including cable, junction boxes
etc, is performed entirely with components
providing double or reinforced insulation (Class II).
• No other electrical equipment apart from Easee
Home/Charge, including lamps and socket outlets,
is connected to the circuit.
• No other conditions identified by the authorized
installer requiring an external RCD.

8
WARNING
Turn off the power before you begin the
installation. Use extreme caution and follow
instructions carefully.
Installation
instructions
1. Bend down the lower part of the rubber cover and
insert the two ends of the supplied tool into the two
openings at the bottom of the front cover.
2. Pull the tool until the front cover comes loose and
remove the cover.
3. Grasp the Type 2 socket and push upwards with
good force until the Chargeberry disconnects.
1
1
1
2
1
3
Opening
Charging Robot
We recommend that you watch the installation
videos available on our website: easee.support.

9
1. Turn off the power before proceeding with the
installation.
2. Fix the backplate to a wall or structure with
sufficient load-bearing capacity using the 4 screws
provided in the mounting kit. Use suitable wall
plugs for mounting and observe the recommended
installation height.
CAUTION
The installation wall must cover the entire back of the
product.
NOTE
If you are going to install multiple backplates, now would
be a good time to mount them as well.
2
Backplate
Mounting
2
130–140 cm
Recommended installation height
2
2
2
2
Backplate
Preparing
3
1. Shorten the sealing plug to fit the cable. The hole
should be slightly smaller to ensure a good seal.
2. Insert the cable through one of the 4 cable entries
and secure it to the backplate with the strain relief
provided.
3. Close all cable entries that are not in use with the
blind sealing plugs supplied.
1 2
3
33
1 2 3

10
1. Strip the individual wires by 12 mm. If the cable has
flexible conductors, it is recommended to use ferrules
on stranded wires. Use correct tools to press them.
2. Tighten the screw terminal with a torque of 5 Nm.
NOTES
— When connecting multiple backplates in parallel,
each screw terminal serves as a coupling point
for adjacent backplates. All backplates must be
connected with the same phase sequence. External
junction boxes or flat cables can be used if it is more
convenient.
— It's recommended to follow the existing colour codes
used in the installation. Depending on national
standards, the colours of the cables can vary from
the illustrations. The illustrations in this manual
follow the IEC 60446 standard.
— Before turning on the power, make sure the wires
are properly connected and tightened. Test this by
pulling on each wire.
Backplate
Wiring
4
PE
2
1
(230 V)
(3x 230/400 V)
(230 V)
(3x 230 V)
TN 1-phase
TN/TT 3-phase
IT/TT 1-phase
IT/TT 3-phase
PE N L1 L2 L3
PE N L1 – –
PE L1 L2 L3 –
PE L1 L2 – –
Tabla de contenidos
Otros manuales de Cargador de baterías de Easee

Easee
Easee Ready Guía de solución de problemas

Easee
Easee Home Guía de solución de problemas

Easee
Easee One Manual de usuario

Easee
Easee Chargeberry Manual de usuario

Easee
Easee Charge Manual de usuario

Easee
Easee Equalizer Manual de usuario

Easee
Easee Charge Lite Instrucciones de montaje

Easee
Easee Ready Instrucciones de montaje

Easee
Easee Equalizer Amp Guía del usuario

Easee
Easee Equalizer Manual de usuario