WAREMA Perea P70 Manual de usuario

Installation Instructions
WAREMA pergola awning
Perea P70
For qualified technicians only
Valid from 14 January 2019
Document number2023753 [Rev.2 - en]
Installation Instructions
WAREMA pergola awning
Perea P70
For qualified technicians only
Valid from 14 January 2019
Document number2023753 [Rev.2 - en]

Table of contents
Page 2 | 22 2023753 [Rev. 2 - en]/2019-01-14
Table of contents
1 Safety and product information........................................................................................ 3
2 Installation......................................................................................................................... 4
2.1 Unpacking the product..................................................................................................................................5
2.2 Scope of delivery..........................................................................................................................................5
2.3 Product position............................................................................................................................................ 6
2.4 Installing the consoles.................................................................................................................................. 7
2.5 Installing the bearing tube............................................................................................................................8
2.6 Preparing the poles (optional)...................................................................................................................... 8
2.7 Erecting the portal........................................................................................................................................ 8
2.8 Attaching the rafters..................................................................................................................................... 9
2.9 Aligning the awning.................................................................................................................................... 10
2.10 Attaching the pole to the mounting substructure....................................................................................... 10
2.11 Securing the rafters permanently............................................................................................................... 12
2.12 Installing the drive shaft............................................................................................................................. 12
2.13 Installing the wall connection..................................................................................................................... 15
2.14 Installing the awning fabric.........................................................................................................................16
2.15 Pulling in the LED line and looping it through........................................................................................... 17
2.16 Attaching the fabric.....................................................................................................................................17
2.17 Installing the LED strip light rail................................................................................................................. 18
2.18 Installing the side cap.................................................................................................................................18
2.19 Line routing................................................................................................................................................. 19
2.20 Setting the motor limit positions................................................................................................................. 19
2.21 Performing a functional check (What to do when?)...................................................................................19
2.22 Connecting the motor on-site..................................................................................................................... 19
2.23 Troubleshooting: wrong motor limit positions............................................................................................. 19
2.24 Finishing the installation............................................................................................................................. 20

Safety and product information
2023753 [Rev. 2 - en]/2019-01-14 Page 3 | 22
1 Safety and product information
Warnings are marked in the instructions with this
symbol.
Read through the product instructions before
use.
Observe all safety and setting instructions.
The basic safety instructions
can be viewed under
(www.warema.de/Sicherheitshinweise).
Target group
These instructions are intended for use by qualified
specialists and fitters.
Permissible activities
Performing tasks on the product that are not described in
these instructions is not permissible. No other alterations
are to be carried out on the product other than as described
in these instructions without the written approval of
WAREMA.
Intended use
The following details apply to the following product: Pergola
awning P70
The product is an external, weatherproof,large-areasun
shading system that may be used for protection against
heat and rain, and for glare control.
Parts description
4
9
8
10
11
7
6
5
12
1
2
3
1Console 7Movable projection
profile
2Motor unit 8Post
3Bearing tube 9Drainage gutter
4Side cover 10 Trim panel
5Rafter 11 Awning fabric
6Travelling horizontal
profile
12 Rain hood
Fig. 1: Parts overview for Perea P70
Wind resistance
The product reaches the following wind resistance: class 3
Use up to Beaufort 7 is permitted.
Beaufort 7 corresponds to a maximum of 17.4m/s and is
defined as a stiff wind, i.e. inconvenience felt when walking
against the wind, whole trees in motion.
The installed product will meet the requirements of the
specified class if the following instructions are observed
during installation:
– The type and number of consoles
– The fixing material used must be suitable for the
mounting substructure (the fitter is responsible for the
right selection).
– The screw anchor pull-out forces specified by the
manufacturer must be taken into account.
– The installation specifications from the fixing material
manufacturer must be adhered to (the fitter is
responsible for adherence).
Depending on the mounting substructure, the wind
resistance class may vary due to the variability of the
building material.

Safety and product information
Page 4 | 22 2023753 [Rev. 2 - en]/2019-01-14
Rain class
The product provides rain protection starting at an
inclination angle of 7° (corresponds to the smallest possible
angle that can be ordered).
Electric drive data
INFO
Observe the separate instructions for the motor.
2 Installation
INFO
The following installation steps are not described in
these installation instructions and can be found in
the accompanying installation note.
Installation of window awning with ZIP guidance
INFO
The fixation and the fixing material must be suitable
for the existing mounting substructure and must be
designed according to the applicable regulations.
INFO
Adhere to the application drawings.
DANGER
Electric shock!
When working in the immediate vicinity of potentially
live parts, such as on-site connecting lines, contact
may result in an electric shock.
Check that the on-site connecting line is de-
energised.
Before installation, de-energise the on-site
connecting line and secure it against being
switched on again.
WARNING
Risk of injury from a falling product!
The product only meets the requirements of the
specified wind resistance class when installed under
certain conditions.
The specified number of fixations and fixing
points must be adhered to.
Observe the information provided by the dowel
manufacturer when installing the product.
INFO
The point of reference for instructions indicating
a side or views is looking from the inside to the
extension direction.

Installation
2023753 [Rev. 2 - en]/2019-01-14 Page 5 | 22
2.1 Unpacking the product
WARNING
Risk of suffocation from carelessness!
Plastic film, polystyrene, small parts, etc., can be
very dangerous for children to play with.
Keep children away from small parts.
Do not leave the packaging material lying around
in disorderly fashion.
INFO
Dispose of the packaging material properly after the
unit is unpacked.
Carefully unpack the product and the individual parts.
CAUTION
Risk of injury from a falling product!
Use of the wrong procedure when pulling the
product up to a higher level with the aid of cables
may result in the product falling down.
Take the product out of the packaging.
Attach the cables to the product in such a way
that they cannot slide off.
The product must be horizontal while it is being
raised.
2.2 Scope of delivery
INFO
Check the scope of delivery against the delivery
note.
Check the parts to make sure they are not
damaged.
Compare the situation on-site with the order
data.
If any items are damaged or not as specified
in the order, stop installation and contact
WAREMA.
Overview of ground connections
Base plate (standard) Field of application
Installation of glass not per-
missible!
Ground installation with
ground screw
Ground installation with
threaded rod
Ground installation di-
rectly on the foundation
Base plate (large) Field of application
Installation of glass permis-
sible.
Ground installation di-
rectly on the foundation
Tab. 1: Overview of ground connections with field of
application

Installation
Page 6 | 22 2023753 [Rev. 2 - en]/2019-01-14
2.3 Product position
H
T
90-190
60-160
60-160
90-190
B
B1
B2
31*
B
BOrder width TOrder depth = wall to back edge of post
HInstallation height (bottom edge of console) 31* Distance from outer edge of side cover
Fig. 2: Dimensional drawing of Perea P70 (all dimensions in mm)

Installation
2023753 [Rev. 2 - en]/2019-01-14 Page 7 | 22
Fixation methods for the poles
INFO
Note the special features of the fixation methods
of the components listed and have any necessary
preparations made.
Pole
Ground installation directly on the foundation [2]
1
2
4
The base plate [1] is at-
tached directly to the foun-
dation [2] using suitable fix-
ing material [4].
Ground installation with threaded rod [6].
61
2
Attach the base plate [1] to
the threaded rod [6] (with-
out intermediate layer).
Ground installation with ground screw [3]
1
3
Attach the base plate [1] to
the ground screw [3] (with-
out intermediate layer).
INFO
When creating the foundation, observe DIN1045
and make sure the foundation-laying area is free
of frost. The edge distances of the fixing points
must be taken into consideration.
The foundation for mounting the base plate must
be poured in accordance with the construction
regulations.
The foundation dimensions must be at least
1000x1000x1000mm.
INFO
The technical requirements for the screw
foundation must be adhered to.
2.4 Installing the consoles
CAUTION
Risk of injury from a falling product!
The number of consoles and the mounting
substructure have a large influence on product
stability. The design is for the following
substructures: full brick, concrete and wood.
Adhere to the number of consoles.
Check the mounting substructure.
Number of rafters Number of consoles
2 pieces 2 pieces
3 pieces 4 pieces
Tab. 2: Number of consoles for the number of rafters
Marking and drilling the fixing points of the consoles
INFO
Pencil in the fixing positions centrally to permit
corrections later on.
H
B
80
X
40
40
Transfer the position
of the consoles to the
mounting substructure
(see Fig. 2). Make sure
the markings are at the
same height.
Hold the console
against the marking,
and make sure it is
properly aligned both
vertically and horizontal-
ly.
Transfer the drill hole
position.
Drill the fixing holes.
Attaching and aligning the consoles
INFO
Check the mounting substructure for
unevenness.
Correct any unevenness.
Attach the consoles.
Align the consoles with
one another.

Installation
Page 8 | 22 2023753 [Rev. 2 - en]/2019-01-14
2.5 Installing the bearing tube
INFO
Observe the tightening torque specifications (min.
tightening torque=25Nm/max. tightening torque
=30Nm).
1
2
3
Mount the bearing tube
in the opening of the
console.
Centre the bearing tube.
Screw in the screws
DIN931 M10x60. Note
the tightening torque.
2.6 Preparing the poles (optional)
INFO
If the water drain in the post is too low, the
connection to the high-temperature pipe (referred to
as the HT pipe below) must be disassembled to be
able to move the cover high up enough to permit the
post to be attached.
1
1
2
3
4
Unscrew the screws
DIN965 5x25.
Remove the cover panel
for the HT pipe.
Remove the retaining
plate for the HT pipe.
Slide the HT pipe into
the post. The HT pipe
is not permitted to pro-
trude.
Slide the cover over the
pole (only if included).
Attach the base plate
to the pole with screws
DIN7500 M8x60.
2.7 Erecting the portal
Attaching the drainage gutter to the post
INFO
The post is flush with the outer edge (higher side) of
the drainage gutter.
1
2
Place the drainage gut-
ter on the post. Note the
position of the drain.
Attach the drainage
gutter using washers
DIN125 8.4 and screws
DIN912 M8x20.
B3
B4
Measure the cover pan-
el [B4] of the window
awning and compare it
with the existing differ-
ence [B3] between the
poles.
1
2
3
If B4 ≠B4, the poles can
be shifted by ±1.5mm. Per-
form the following steps.
Release the screws on
both sides.
Move the poles by the
difference.
Tighten the screws.
Erecting the portal
Fig. 3: Erecting, aligning and securing the portal
Erect the portal. Centre the position (see Fig. 2/Page 6)
and roughly align the portal with the bearing tube.
Attach braces to secure the portal against falling over.

Installation
2023753 [Rev. 2 - en]/2019-01-14 Page 9 | 22
Attaching the bearing part
Attach the bearing parts
with screws DIN912
M8x25 to the slot nuts
in the drainage gutter.
It should still be possi-
ble to move the bearing
parts.
31
Move the outer bear-
ing parts to the speci-
fied position; the middle
bearing part (if present)
is centred.
Tighten the screws.
2.8 Attaching the rafters
INFO
Beads are inserted in the
outer rafters.
The bead must face
inwards.
Order width Number of rafters
Up to 4000mm 2pieces
From 4001mm 3pieces
Tab. 3: Number of rafters for various order widths
Attaching the middle console in the bearing tube
INFO
Begin with the middle rafter, if present.
Attach the console in
the bearing tube.
Move the rafter to posi-
tion. Note the order data
(Fig. 2).
Screw in the screw
DIN912 M8x30. The
console is now secured
against detachment.
Rest the rafters on the portal.
Attaching the outer consoles to the bearing tube.
INFO
The bead on the rafter must face inward.
Attach the console in
the bearing tube.
5
Move the rafter to posi-
tion. Note the order data
(Fig. 2).
Screw in the screw
DIN912 M8x30. The
console is now secured
against detachment.
Secure the console
against becoming de-
tached.
Rest the rafters on the portal.

Installation
Page 10 | 22 2023753 [Rev. 2 - en]/2019-01-14
Connecting the rafter with the drainage gutter
Insert the head piece in
the recess of the bear-
ing part.
Attach the head piece
on the bearing part
with the screw DIN912
M8x35.
Installing the front trim panel
1
2
1Trim panel 2Screws DIN7984
M8x16
Fig. 4: Installing the trim panel
INFO
Position the trim panel above the last runner. It will
be aligned to the final position later on.
Slide the slot nuts to the
correct position and se-
cure them. Slot nuts are
not clamped and may
slide off.
Screw in the screws
DIN7984 M6x16 into
the slot nuts through the
trim panel.
2.9 Aligning the awning
D1
D2
D3
D4
31
Fig. 5: Measuring the diagonals (Perea P70)
Measure the diagonalsD1 and D2 or D3 and D4
(depending on the number of rafters). If D1/D3=D2/D4,
the rafters are parallel and at right angles.
Move the portal if necessary and check the diagonals
again.
2.10 Attaching the pole to the mounting
substructure
INFO
The edge distances of the fixing points must be
adhered to.
Drilling the fixing holes
INFO
Applies to screw foundation
Transfer the position of
the posts to the mount-
ing substructure.
Raise the rafter and move the portal toward the bearing
tube.
Mount the ground screw into the mounting substructure.
INFO
Applies to ground installation directly on the
foundation or ground installation with a threaded rod.