VP SSR 900 Manual de usuario

VARCO PRUDEN BUILDINGS
SSR 900 Seamer Tool Manual
The field guide for proper use of the Model 900 SSR Seamer Tool.

The builder/Erector remains solely responsible for the
safety and appropriateness of all techniques and methods
utilized by its crew in the erection of the VP building.
The Builder/Erector is also responsible for supplying any
safety devices, such as scaffolds, runways, nets, etc. which
may be required to safely erect the metal building system
and to perform the SSR-Seaming Operation.
Unplug the electrical power source before performing
any service on the seamer tool.
Check and maintain all electical cords and connections.
Power source and electrical cords should have a 3 wire
grounding system.
Discontinue seaming operation in damp, wet conditions and
other undesirable weather conditions.
Provide safe operating procedures along edges of roof,
tuf-lites, and other roof openings.

1. SSR Seamer tool Kit Components.............................................2
2. Basic Description.......................................................................3-4
3. Preparation for Seaming............................................................5
4. Seaming Operation/Start/Endlaps/Finish...................................6-9
5. Power Source............................................................................10
6. Field Maintenance/Troubleshooting..........................................11-13
7. Seaming Information.................................................................14
8. Hand Crimping/Information.......................................................15
1. VP-SSR Hand Crimping Tool...................................................18
2. Uses of Hand Crimping Tool....................................................19
3. Step 1: Positioning...................................................................20
4. Step 2: Crimp Female Leading Edge.......................................21
5. Step 3: Crimp Finish End.........................................................22
6. Notes........................................................................................23
Item
Item
Page No.
Page No.
1
9. Seamer Adjustment..................................................................16-17

1. SSR Seamer Tool With Handle Assembly
2. Lubrication Gun
3. Field Manual
4. One (1) Finish Seam Gauge & Instructions
5. Shipping Box. Save for
Storage & Shipping.
VP-Tool
Serial
No.
Model No. VP-900
2
Do Not Discard.
1. SSR SEAMER TOOL KIT COMPONENTS

1. The SSR Seamer Tool is a special precision designed and built, portable
roll-forming machine.
2. The tool is powered by an electronic motor, rated at 1/2 H.P./.8 Amp/115 volt/60
cycle single phase.
3. The Seamer Tool is lightweight 38lbs.
4. Forming speed is capable of 25 surface feet per minute.
5. Power required: 20 Amp breaker minimum.
6. Control: on/off switch, forward single speed.
Down Slope
7. Each of the three (3) sets forming rolls and one (1) guide roll perform a part
of the seaming operation.
6
3
5 4
12
Clamping Handle
PLAN VIEW
FORMING ROLLS
As viewed from bottom
Moveable
Fixed Side
Front
Side
Model No. VP-900
Seaming
3
2. BASIC DESCRIPTION

8. Guide Roll and Forming Rolls.
a. Front Guide Roll-Fig. 1
When seamer tool is clamped on seam
correctly, guide roll should be in
position as shown.
b. First Set (Rolls #1 & 4)-Fig. 2
Tuck the female lip under the male lip
and begin to pull the seam together.
c. Second Set (Rolls #2 & 5)-Fig.3
Force the two parts of the seam together
and begin the finishing process.
(#2 roll-fiber roller)
d. Third Set (Rolls #3 & 6)-Fig. 4
Finish the seaming process by compressing
the seam.
FIG. 1
FIG. 2
FIG. 3
FIG. 4
41
52
63
Top Guide
Roll
Model No. VP-900
4
2. BASIC DESCRIPTION (CONT'D)

3
4
2
1
A. Check Seamer Tool
1.Check seamer tool for grease.
When in use, tool should be
lubricated every day. If Seamer
tool is in sustained, continuous use,
grease every four (4) hours. Only
one (1) shot of grease required
at each point shown (1, 2 & 3).
2.Lubricate tool at grease fittings,
using only "Lithium Grease"
See figure 1 for grease fitting
locations.
3.Clean forming rolls with WD-40
to remove dirt, excessive grease
and sealant build-up on rolls.
4.Check tool for loose parts,
screws,wheels,forming rolls, and
and electrical connections. Repair
and replace as required.
5.Lubricate drive chain, which is
enclosed under rear chain cover.
Loosen and remove one (1) set
screw from cover. Apply one (1)
shot of grease to each drive
sprocket as required after 8 hour
use (see figure 4 above).
B. Panels
1. Panels may have excess oil build-up. This will not affect the
seaming operation. Panels should be wiped down at the areas
where tape mastic or tube sealant is to be applied.
2. Check seams to ensure they are engaged prior to seaming.
See and below.
MALE RIB
SEALANT
FEMALE RIB
SEALANT
FEMALE RIB
MALE RIB
FIG. 1
CORRECT
FIG. 1 INCORRECT
FIG. 2
Model No. VP-900
Figure 1 - Correct Figure 2 - Incorrect
5
3. PREPERATION FOR SEAMING
Clean Mastic from roller daily.

NOTE:
Start SSR-Seamer Tool is designed to operate one direction only.
See caution and safety information in front of this manual
TO BEGIN SEAMING OPERATION
1. Ensure proper engagement of the male and female hems.
Hand crimp with VP hand crimping tool or channel lock type
SEAM DIRECTION
1"
TUCK SEAMPROPER ENGAGEMENT
pliers. (See Hand Crimping/Information)
Model No. VP-900
6
4. SEAMING OPERATION/START

Panel
Edge First (2) Stands
of Rollers
Panel
Edge
6 5 4
3. Clamp handles 4, 5 & 6 down to the locked position.
2. Position seamer on the beginning edge of the SSR
Panel, so that the first two stands of rollers
straddle the seam and rest on the panel.
6 5 4
Model No. VP-900
Direction of Seamer
Travel
Direction of Seamer
Travel
Clamp Handles
Down
7
4. SEAMING OPERATION/START

6 5 4
0.45" Max
PROPER SEAM PROFILE
AFTER SEAMING
4. Turn Power Switch on and run seamer about 4 inches.
Check seam to ensure proper seaming operation.
5. After seam is checked and proper operation is verified,
continue to seam remainder of panel, inspecting seam
continuously. Seamer should travel approximately 25 feet
per minute.
6. When the seamer tool approaches the end lap, "STOP"
the seamer tool before crossing the End Lap and hand
crimp the leading edge of female lip. Also, it will slow
down due to the additional thickness of metal. This
heavier load requirement can be detrimental to the
seamer tool if it should come to a complete stall. The
operator should assist by manually pushing the seamer
forward by the handle until the seamer clears the lap.
HAND CRIMPING AT START OF SEAMING OPERATION:
CRIMPING THE FEMALE LIP OF SEAM INTO POSITION.
7. When approaching the end of the panel, use extreme
caution, and stop seamer while rear wheels remain on
panel. Roll machine back to a safe working area.
Preform/hand
crimp approx. 1" female lip
TUCK LIP
CHANNEL LOCKS
Model No. VP-900
CAUTION:
8
4. SEAMING OPERATION/START
@ CENTER OF
SSR CLIP
Tabla de contenidos