4 Quick Reference K0458 Revision B - [EN] English
S3 PV 623G models: Start operations
WARNING
Pressurized gases and fluids are dangerous. Before connecting or disconnecting pressure equipment,
safely release all the pressure (Ref: K0457, 4.3, Release the pressure).
Caution: To prevent damage to the pressure station, do not let dirt get into the pressure mechanism.
Before connecting equipment, make sure it is clean.
S3.1 Release the pressure/Attach the device under test
Note: Fill the reservoir before attaching the device. (Ref: figure A4).
S3.2 Filling, priming and generating pressure (Ref: Figure A4). Fill the reservoir
using the procedure that follows:
Caution: Ice in the pressure mechanism can cause damage. If the temperature is less than 4°C
(39°F), drain all water from the PV 623G pressure station.
When using the PV 623G pressure station for the first time, fill the reservoir with the correct hydraulic
fluid (Ref: K0457 Table 7.1 General specification PV 62XG). Fill and prime the pressure station.
S3.3 Filling and Priming
Step Procedure
1. Open the refill valve fully counter-clockwise (Ref Item 10).
2. Open the pressure release valve counter-clockwise (1 turn) (Ref Item 4).
3. Use the applicable adaptor to attach the device, (Ref: figure A3, Item 2).
Step Procedure
1. If new, remove the red plastic blanking cover from the Test port.
2. Turn the Refill valve fully counter-clockwise.
3. Turn the Volume adjuster fully clockwise.
4. Turn the Release Valve Stem fully counter-clockwise.
5. Remove the Priming pump piston/Release valve stem assembly
6. Fill the reservoir with the recommended fluid, (Ref: K0457 Table 7.1 General
specification PV 62XG) 25mm approx from the top.
7. Re-fit the Priming pump piston/Release valve stem assembly
8. Turn the Release Valve Stem fully clockwise.
9. Turn the Refill valve fully clockwise, until finger tight.
10. Turn the Volume adjuster fully counter-clockwise.
11. Turn the Volume adjuster 5 turns clockwise.
12. Operate the Priming pump until the air is expelled and fluid is visible at the Test port.
13. Fit the “Item under test” to the Test port use the existing adaptor or the applicable AMC
adaptor and applicable seals.
14. Operate the Priming pump and prime the system to a maximum pressure of 10 bar.
A2.3 (Front cover)