Figure 5: Safety sticker for the pre-installed circuit breaker
1. First shut down the liveX. To do this, you have to select the "Shut down" button in the portal in the
system settings (see also 4.V). 30 seconds after selecting, the liveX is completely shut down. Now
switch OFF the power supply of the liveX (Figure 3, point 3).
2. Switch OFF the output of the H10 inverter. To do this, press the "OFF" button below the H10 inverter
display (Figure 2, point B). As soon as the output is deactivated, the bypass light is activated (Figure 3,
point 5). To completely turn off the system output, the residual current circuit breaker (Figure 3, point
4) must be turned OFF.
3. Now switch OFF all photovoltaic inputs. To do this, the photovoltaic input breakers 1-4 must be
switched OFF (Figure 3, point 2).
4. Now switch OFF the battery module breakers 1-4 (Figure 3, point 1). In addition, all ON/OFF switches
(Figure 4, item 7) of each battery module must now be set to position 0.
5. Afterwards the pre-installed circuit breaker of the batterX system must be switched OFF.
The system is now completely shut down and the input and output of the system have been disconnected.
START UP AND SWITCHING ON
After a complete shutdown the batterX system, you can use this guide to restart and switch ON the system:
1. Make sure that all wires, cables or connectors are connected correctly.
2. The first step is to switch ON the main circuit breaker of the batterX system again.
The H10 inverter is now started automatically.
3. Now all ON/OFF switches (Figure 4, item 7) of each battery module must be switched to position 1.
The battery module circuit breakers 1-4 (Figure 3, point 1) can now be switched ON.
4. Next all photovoltaic input circuit breakers 1-4 (Figure 3, point 2) are switched ON.
5. The next step is to activate the output of the H10 inverter. To do this, push the "ON" button below the
H10 inverter display (Figure 2, point A). The H10 inverter will now synchronize and fully power up.
During synchronization, it will turn ON and OFF several times. This process can take up to 3 minutes.
As soon as the bypass signal light (Figure 3, point 5) is switched OFF, the H10 inverter is ready for
operation.
6. Finally, the power supply of the liveX (Figure 3, point 3) and the residual current circuit breaker (Figure
3, point 4) can be switched ON again.
Switching ON the liveX is completed after 30 seconds and the batterX system is fully operational